Sanctuary Ponds, Wongawilli Stages 1 to 3

Project Summary:

Menai Civil delivered a multi-stage residential subdivision comprising 214 residential lots across three stages, with Stage 3 completed over a 12-month period. The works included bulk earthworks, road and pavement construction, stormwater drainage, utility reticulation, shared paths, retaining walls and extensive landscaping across the development.

A key component of the project was the implementation of a Remediation Action Plan to address coal-wash and asbestos-impacted soils. The works required careful management of contaminated materials and stringent surface water controls to protect the surrounding environment, including adjacent dams and more than 15,000 m² of riparian corridor planting. The project also included the installation of pedestrian bridges to improve connectivity throughout the development.

Scope of Works:

  • Approximately 54,250 m³ of bulk earthworks.

  • Implementation of a Remediation Action Plan across the development.

  • Remediation and removal of soils impacted by coal wash and asbestos contamination.

  • Construction of approximately 26,600 m² of flexible pavement, including sub-base, base, spray seal and asphalt.

  • Construction of more than 9,500 m² of concrete shared paths and kerbs.

  • Installation of more than 3,100 m of reinforced concrete stormwater drainage.

  • Installation of sewer, potable water, electrical and NBN service reticulation.

  • Construction of retaining walls and pedestrian bridges.

  • Installation of signage and line marking.

  • Traffic management and control throughout construction.

  • Landscaping and streetscape works, including more than 15,000 m² of riparian corridor planting.

Client: Newquest Property

Superintendent: Cardno (now Stantec)

Value: $13.5 million

Commenced: May 2018

Completed: May 2019

Location: Illawarra Region, NSW